Timeline
So here is the project’s timeline. I will update this as things get done and hopefully stick to it.
Phase 1: (1 week) deadline: June 7th
- Sketch and perfect the wireframe (5 days)
- Define the use cases (5 days)
- Install Trac/SVN, setup CakePHP (1 day)
- XHTML the wireframe (2 days)
- XML the use cases (2 days)
- Select a name (7 days)
Phase 2: (2 weeks) deadline: June 21st
- Design web app (11 days)
- XHTML web app (3 days)
- Install, test and optimize the required vendor classes (2 days)
- Code the required extra classes (5 days)
- Draw the general architecture (site, web app, web services, database, etc.) (1 day)
- Write the teaser page to recruit early-users (1 day)
- Design the database (2 days)
Phase 3: (4 weeks) deadline: July 19th
- Design and implement teaser page (2 days)
- Develop web app (28 days)
- Design site (6 days)
- Design logo (10 days)
- Copy writing for the website (12 days)
- XHTML website (5 days)
Phase 4: (2 weeks) deadline: August 2nd
- Testing (14 days)
- Add new third parties (10 days)
- Write and distribute press release (2 days)
- Launch