Timeline

Posted by Jad on June 01, 2007

So here is the project’s timeline. I will update this as things get done and hopefully stick to it.

Phase 1: (1 week) deadline: June 7th

  • Sketch and perfect the wireframe (5 days)
  • Define the use cases (5 days)
  • Install Trac/SVN, setup CakePHP (1 day)
  • XHTML the wireframe (2 days)
  • XML the use cases (2 days)
  • Select a name (7 days)

Phase 2: (2 weeks) deadline: June 21st

  • Design web app (11 days)
  • XHTML web app (3 days)
  • Install, test and optimize the required vendor classes (2 days)
  • Code the required extra classes (5 days)
  • Draw the general architecture (site, web app, web services, database, etc.) (1 day)
  • Write the teaser page to recruit early-users (1 day)
  • Design the database (2 days)

Phase 3: (4 weeks) deadline: July 19th

  • Design and implement teaser page (2 days)
  • Develop web app (28 days)
  • Design site (6 days)
  • Design logo (10 days)
  • Copy writing for the website (12 days)
  • XHTML website (5 days)

Phase 4: (2 weeks) deadline: August 2nd

  • Testing (14 days)
  • Add new third parties (10 days)
  • Write and distribute press release (2 days)
  • Launch